Unyte was contracted to undertake floodway rehabilitation works on Yeungroon Road in Charlton.
Unyte’s scope of works included:
Removal of existing road surface and excavation to subgrade height of road
Placement and compaction of pavement layers
Concrete pavement
Asphalt of road surface
Installation of road signage
Installation of kerb
Unyte successfully engaged with local contractors and suppliers, which were limited in the area, as well as working with the local community ensuring access was maintained to their businesses and residential properties.