Melbourne Airport Value South Car Park

Project completion June 2026
Location Melbourne, VIC
Client Australia Pacific Airports Melbourne (APAM)
Sectors Transport, Ports, Airports

Expanding capacity for Melbourne’s busiest gateway.

The Melbourne Airport Value South Car Park expansion delivered critical additional parking capacity to support the continued growth of Melbourne Airport and improve the travel experience for passengers during peak holiday periods. Located at the corner of Airport Drive, Apac Drive and Francis Briggs Road, the project transformed the existing area into a modern, high-capacity sealed car park designed to improve accessibility, operational efficiency and customer convenience.

Delivered within a live airport environment, the project required careful staging and coordination to maintain ongoing parking operations throughout construction. Working closely with APAM, the team successfully balanced operational requirements with construction delivery, ensuring the airport remained functional and accessible during high-demand embargo periods.

860+

New car parks

25kt+

Recycled crushed concrete

3km

Drainage installed

3

New structures
Building. Better. Together.

Symal proudly delivered the expansion of Melbourne Airport’s Value South Car Park within one of Victoria’s busiest live operating environments, carefully staging works to keep the airport moving through peak holiday periods. Across Christmas and Easter embargo windows, large sections of the car park were progressively handed back to APAM to support increased passenger demand, while construction safely continued around active traffic, pedestrians and public transport movements.

The project transformed the existing area into a modern, high-capacity facility, delivering over 860 new sealed asphalt car parking spaces with improved access from Airport Drive and Francis Briggs Road. New entrance canopies, bus facilities, accessible amenities and smart parking technology including licence plate recognition systems, boom gates and automated tyre spikes were delivered alongside extensive underground infrastructure upgrades across the site.

More than just a car park expansion, the project focused on improving the overall customer experience for travellers arriving at Melbourne Airport. New lighting, CCTV, landscaping, wayfinding, pedestrian pathways and street furniture helped create a safer, more accessible and easier-to-navigate environment, while temporary bus shelters, lighting and pedestrian access were maintained throughout construction to minimise disruption for passengers and airport operations.

Sustainability outcomes were also embedded throughout delivery, with recycled crushed concrete reused across pavements and backfill material, alongside recycled asphalt pavement incorporated into surfacing works. The team also successfully managed PFAS-affected areas through additional testing and careful material handling, helping minimise unnecessary offsite disposal while maintaining environmental compliance across the project.

  • 2025 • September – November

    Site establishment and early works

    Site establishment and staged construction works commenced, including bulk earthworks, drainage installation, underground services, temporary traffic management and temporary facilities to maintain parking operations, pedestrian access and bus connectivity throughout construction.
  • 2025 • December

    Christmas holiday handover

    More than 450 completed car parking spaces across the western half of the site were temporarily handed back to APAM ahead of the Christmas holiday period, supporting increased passenger demand while construction activities paused during the embargo period.
  • 2026 • January – February

    Main civil and pavement works

    Construction recommenced following the holiday embargo period, with major civil, pavement, drainage and underground infrastructure works progressing across the remainder of the site, alongside continued staging to maintain airport functionality and safe public access.
  • 2026 • March – April

    Structures, lighting and operational systems

    Entrance canopies, bus facilities and associated structures were completed, alongside lighting commissioning, CCTV, security systems, communications infrastructure and installation of automated parking and access systems across the site.
  • 2026 • April

    Easter holiday handover

    More than 90% of the completed car park was handed back to APAM ahead of the Easter holiday period, ensuring additional parking capacity was available to support peak airport operations and passenger movements.
  • 2026 • May – June

    Finishing touches and opening

    Final line marking, signage, boom gates, ticketing systems, landscaping and finishing works were completed ahead of final handover. Following an opening event, the expanded Value South Car Park officially opened to the public on 1 June 2026, delivering improved parking capacity and customer experience for Melbourne Airport passengers.
  • Symal Infrastructure
  • | Contracting
  • | Transport
  • | Ports
  • | Airports

Related projects

Explore our work

We've been leaders in the construction industry for over 20 years, proudly delivering Australia’s biggest civil construction projects.