Merrygoen and Ukebung Creek Bridge Replacement

Project completion December 2021
Location Merrygoen, NSW
Client Australian Rail Track Corporation
Sectors Bridges and structures, Rail infrastructure

Our Bridge & Civil team completed a two part project comprising of an intensive and complex 82 hour rail bridge replacement at Merrygoen, NSW.

During the occupation, our team replaced two existing timber bridges with two new concrete culvert structures on the CNW rail line designed to minimise the ongoing emergency maintenance of the existing structures, as well as increasing the bridge load capacity and providing improved maintenance accessibility of the structures.

The improved bridge will contribute to the reliability and overall track performance within ARTC’s CNW network.

  • Symal Infrastructure
  • | Civil construction
  • | Bridges and structures
  • | Rail infrastructure

Related projects

Career you can brag about? Make it yours.

If you're looking to build an exciting future, let's talk about the part you can play in creating a better tomorrow. Together, we can make amazing things happen.