Working with the Department of Defence's Land Engineering Agency, Wamarra replaced a problematic section of roadway at at Monegeetta Proving Ground, improving access to their brake testing strip.
The scope of work included:
Demolition and removal of 1000m2 of existing asphalt pavement and crushed rock
Widening the roadway
Installation of 1450m2 of new pavement
Despite challenges with subgrade conditions, we received recognition for our high-quality work and successfully addressing issues with minimal impact on the project timeline through close collaboration with geotechnical engineers.