Engaged by BEON Energy Solutions, Symal spearheaded early works, focusing on constructing crushed rock access roads and preparing hardstands that were used throughout the project's duration. In additional to this, we undertook trenching for AC cables, DC cables, communications cables, and earthing cables, encompassing excavation, benching, battering, conduit and electrical infrastructure installation, backfilling, and compaction.
Navigating challenges, particularly in a low-lying flood plain area, demanded proactive measures to mitigate cold weather effects. The ETP Solar Farm, boasting 39,000 PV modules, alongside six Power Conversion Units and weather stations, represents a monumental feat in sustainable energy infrastructure.