Tarratarra Stadium has been delivered as part of the Victorian Government’s Regional Sports Infrastructure Program. The new multi-sport facility provides high-quality sporting and community infrastructure to support Armstrong Creek’s growing population, creating more opportunities for sport, recreation and social connection.

Located in the heart of Armstrong Creek, the development brings together four indoor multi-sport courts, a café, community gathering spaces and a civic plaza with outdoor areas for recreation and events. New car parking, including electric vehicle charging stations, further supports accessibility and everyday use. The facility is fossil-fuel free, fully electric and on track to achieve a 5-Star Green Star rating.

5,300

m² concrete slab

1,000+

tonnes of reinforcement

12,000+

local plants
Building. Better. Together.

Symal delivered key civil, structural and landscaping works at Tarratarra Stadium, helping bring a new sporting and community destination to life in one of Victoria’s growing residential precincts. Engaged by Fairbrother Construction, the project involved coordinating works across the building footprint, car park and surrounding public spaces to support the development’s broader vision.

Structural works included the installation of footings and a 5,300m² building slab, with more than 1,000 tonnes of reinforcement bent and tied on site. Civil works covered stormwater drainage, pavements and car park construction, providing the essential infrastructure to support the stadium and its surrounding facilities.

The project’s landscaping helped shape the public spaces surrounding the stadium, with hardscape works including exposed aggregate and coloured and plain grey concrete footpaths, tiered seating and custom timber seating. Soft landscaping added more than 12,000 local provenance plants, alongside mulch and turf, bringing greenery to the precinct and creating welcoming spaces for people to gather.

At the centre of the development, the civic plaza provides an accessible link between Armstrong Creek Town Centre and the future public transport station. With open public areas designed for community events, informal recreation and everyday use, the completed space supports greater connectivity and gives the growing community another place to meet, move and spend time together.

Tarratarra Stadium adds to Armstrong Creek’s recreational offering, combining sporting facilities with thoughtfully designed public spaces to support participation, community connection and the area's continued growth.

  • 2025 • April

    Site establishment and bulk earthworks

    Site establishment commenced, including the construction of haul roads and implementation of environmental controls. Bulk earthworks followed, with site stripping and cut-and-fill operations preparing the area for construction.
  • 2025 • May – September

    Structural footings and building slab

    Detailed excavation and preparation of ground beams, pile caps and raft footings progressed alongside the structural works. The team delivered the 5,300m² building slab, forming a key part of the stadium’s foundations.
  • 2025 • July – November

    Civil drainage installation

    Stormwater drainage was installed across the site, establishing essential infrastructure to support the stadium, car park and surrounding public spaces.
  • 2025 • November – 2026 • July

    Car park construction

    Car park construction progressed to provide parking infrastructure for stadium users and visitors, supporting access to the new sporting and community facilities.
  • 2026 • March – July

    Civic plaza and hard landscaping

    Hard landscaping works took shape across the precinct, including exposed aggregate, coloured and plain grey concrete footpaths, reinforced concrete tiered seating and custom timber seating. These works helped establish the civic plaza and its surrounding public spaces.
  • 2026 • June – August

    Soft landscaping and planting

    Landscaping continued with the installation of more than 12,000 local provenance plants, alongside mulch and turf, adding greenery to the precinct and completing key outdoor areas.
  • 2026 • October

    Project completion

    Tarratarra Stadium was successfully delivered, providing Armstrong Creek with a new multi-sport facility, expanded recreational opportunities and welcoming public spaces designed to serve the growing community.
  • Symal Contractors
  • | Contracting
  • | Community infrastructure
  • | Sports and recreation

Related projects

Explore our work

We've been leaders in the construction industry for over 20 years, proudly delivering Australia’s biggest civil construction projects.